Title: Nevada Outlook
Post by: cl94 on July 03, 2023, 12:23:26 am
Making a list of all the upcoming Nevada projects that are likely to affect TM. All of these projects are pulled from Nevada's STIP and federal work program. That is, they're all funded and construction is almost certain.

Second half of 2023 to first half of 2024- lucky for us, all of the super important medium-term projects are in here

Out to 2026 (and beyond if funded)
Title: Re: Nevada Outlook
Post by: cl94 on January 01, 2024, 12:42:13 am
We're probably looking at Q1 2024 for I-11 north to NV 157. I can confirm that, as of November, signs have been installed along I-15 SB reflecting I-11's extension. I-515/US 95 itself had no reference to the extension, while CC 215 had covered I-11 shields. Newspaper report: https://www.reviewjournal.com/news/news-columns/road-warrior/i-11-footprint-to-grow-in-southern-nevada-2967497/

IMO, at least one of four things needs to occur to make the change here, none of which has happened yet:


Still no word on CC 215, but construction is substantially complete. AFAIK, NDOT has not yet submitted an application to extend I-215. Given how long it took for the southeast leg to be added to the state highway system, it is possible that other relinquishments may not occur for years.

It probably makes the most sense to keep I-515 as an alternate name for I-11
Title: Re: Nevada Outlook
Post by: cl94 on January 15, 2024, 12:58:13 am
New Nevada route log came out at the beginning of the year and is linked here: https://www.dot.nv.gov/doing-business/about-ndot/ndot-divisions/planning/roadway-systems/state-maintained-highways-descriptions-index-maps

Nothing major in there that hasn't already been accounted for. A note was added saying that a redesignation of I-515 as I-11 is imminent, but it has not yet occurred. Weirdly, a short segment of SR 529 in Carson City was added back into the system, but it is unsigned as of last week and entirely concurrent with US 395 Business. If signs are put up for SR 529, it will be added. The disconnected northern segment of SR 596 that was added last year is remaining out pending confirmation that it has become signed. It is possible that it will never be signed, as SR 596 is a route that is being uploaded in segments for reconstruction and then quickly relinquished.