It looks like completion has been pushed to the end of 2022.

Markkos1992:
Latest update from the MD 97 Brookeville Bypass website:  https://mdot-sha-md97-brookeville-bypass-mo7465171-r-maryland.hub.arcgis.com/


--- Quote ---Fall 2022: Crews continue project activity for construction of the new road for the project. Weather permitting, the new road could open by late fall--weather and progress permitting, As a result, the Brookeville Road closure will remain in effect until the new mainline road opens.
--- End quote ---

Markkos1992:
Latest Update:


--- Quote ---Winter 2022: The project is now 85 percent complete. The previously communicated estimated completion date for the project was year-end 2022. The new estimated completion date is late summer 2023. A redesign of a bridge for the project has pushed back the final paving schedule until next year. Through late spring, limited work on the project will continue, weather permitting.
--- End quote ---

Markkos1992:
The Brookeville Bypass on MD 97 apparently opened yesterday.  (https://mdot-sha-md97-brookeville-bypass-mo7465171-r-maryland.hub.arcgis.com/)


--- Quote ---May 2023: The Brookeville Bypass will officially open the week of Sunday, May 21st. Crews will perform a traffic switch on the morning of May 21st to open the newly constructed bypass to the traveling public. This switch will not affect County roads. Variable Message Signs (VMS) are in place to notify motorists of the upcoming change.
--- End quote ---

There goes my 100% clinch of MD until probably this weekend.   :D

dave1693:
I guess my next trip between VA and PA will have to use MD 97 to reclinch it.