Highway Data Discussion => 6-Month+ Outlook => Topic started by: Markkos1992 on July 11, 2022, 11:40:24 am

Title: IN: I-65/US 52 New Exit at CR 500 near IN 267
Post by: Markkos1992 on July 11, 2022, 11:40:24 am
https://wyrz.org/upcoming-i-65-lane-restrictions-near-whitestown-beginning-may-11/

Quote
This project was awarded to Beaty Construction for $62.8 million. The project includes building a new interchange on I-65 at Boone County Road 550 South and redesigning the I-65 and S.R. 267 interchange. Both will be Diverging Diamond Interchanges, (DDI). The contract completion date is set for August of 2022.

Wikipedia is referring to the new Exit as Exit 130.

EDIT:  Wikipedia is now referring to it as Exit 131.
Title: Re: IN: I-65/US 52 New Exit at CR 500 near IN 267
Post by: mapcat on July 24, 2022, 05:47:29 pm
Okay, thanks. There's already an Exit 130 at Whitestown Pkwy so when someone sees what the new exit actually is called please post that here and I will add it.