Title: MI: MI-5 extended to Cass Avenue in Detroit
Post by: dfilpus on December 25, 2016, 10:27:47 am
According to Michigan Highways, http://michiganhighways.org/listings/M-005.html, in April-May 2016, MI-5 was extended from I-96 to Cass Avenue in Detroit replacing an internal unsigned state trunkline route (designated internally by MDOT as "Old BS I-96"). The extension is fully signed and has an END MI-5 bannered shield at Cass.
New waypoints should be at Livernois Ave, Joy Rd and Grand Blvd (all for access to I-96 interchanges), I-94, MI-10, I-75.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: mapcat on December 26, 2016, 08:33:11 pm
Good catch. MDOT hasn't caught up with the change yet in their public GIS (https://mdotnetpublic.state.mi.us/drive/), but I found one of the new markers just west of Cass:

https://www.google.com/maps/@42.3345498,-83.0544855,3a,15y,316.32h,88.72t/data=!3m6!1e1!3m4!1sR8UAVDqZbd3zUtDApyFmfA!2e0!7i13312!8i6656 (https://www.google.com/maps/@42.3345498,-83.0544855,3a,15y,316.32h,88.72t/data=!3m6!1e1!3m4!1sR8UAVDqZbd3zUtDApyFmfA!2e0!7i13312!8i6656)

Those waypoints make sense, as does one at I-96(187). All added, and point locations were adjusted to match the Grand River Ave overpasses at each interchange.

Submitted.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: michih on December 27, 2016, 03:39:30 am
Submitted.

Does it mean the topic can be marked solved (and removed to "Solved Highway data updates" one day)?
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: mapcat on December 27, 2016, 08:51:19 pm
Does it mean the topic can be marked solved (and removed to "Solved Highway data updates" one day)?

Yes, but I'd like to wait a few days for comments.

Let's be patient. When I responded, I had just submitted the pull request, so the site hadn't been updated yet. Jim's schedule might not permit immediate updates for a while, so it's likely the OP won't see confirmation of the change right away, which also tells me the comment shouldn't disappear prematurely.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: Jim on December 28, 2016, 09:43:59 am
Re: moving topics to solved, I don't think there needs to be a great rush.  I'd like to see the topics left unlocked and not moved to solved for maybe a week minimum after a fix is live on the site.  Those who made the fixes can go through occasionally to move things to reduce clutter but I don't think there's any harm if that only happens say every couple weeks or once a month.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: dfilpus on December 28, 2016, 10:42:59 am
On the updates page, the fix for this references MI-10, instead of MI-5.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: yakra on December 28, 2016, 01:40:19 pm
My two cents:
Marking as solved is no problem; the OP can still reply to the thread.
Moving something to the "solved" subforum is no issue for me personally, as I follow the "O HAY, new posts here" icons from the front page to find new & updated threads. Looking for an updated thread in "solved" should be pretty intuitive, but I can see it as being easier/more intuitive for some users to just go find the thread in the subforum where they originally posted it.
Title: Re: MI: MI-5 extended to Cass Avenue in Detroit
Post by: Jim on December 28, 2016, 04:52:05 pm
On the updates page, the fix for this references MI-10, instead of MI-5.

I'll fix this for the next update, thanks.